The plan for our project is to host a Pro Evolution Soccer Tournament. The client for this project will be students at John Ruskin College. The aims and objectives for this project are to gain profit and gain customer satisfaction.

Extracts from this document...

Introduction

Task 1 Plan The plan for our project is to host a Pro Evolution Soccer Tournament. The client for this project will be students at John Ruskin College. The aims and objectives for this project are to gain profit and gain customer satisfaction. The venue for the launch of this project will be within the college, which is in room C56. We will need �5 for prize money, �10 for a trophy and �7.50 for three plain black t-shirts. These will be worn by the three co-ordinators of the tournament. Health and Safety check list Our Health and Safety procedures will be to check that loose wires are placed out of the reach of the clients while the tournament is running. ...read more.

Middle

Each game will last up to five minutes. A draw will be followed by extra time if both teams fail to find a winner. If is still not yet decided, it will be decided with a penalty shootout to determine who progressed to the next round (at least five penalties each, and more if necessary). Task 2 Donations towards this task will come from the college, who will give us our budget and allocate us a room to stage the tournament. The main advantage of staging this event within a college class room such as C56 will be that competitors would not have to go far and wide to play, as it is in the college. ...read more.

Conclusion

Budgets and targets have been confirmed and for the competition to get up and running, a total of �22.50 will be needed so that all basic deadlines are met. Our budget includes �10 for a trophy, �7.50 for the T-Shirts and �5 for the prize money given to the winner. We also have a donation from a source in the form of a friend, who will print the three black t-shirts for free. It will have 'Pro Evolution Soccer Contest' printed on the back. We have run and tested all resources needed for the project and have come to noticed that there was no potential difficulties towards prior implementations. Therefore, no extra resources will be needed to run the project, as all seems to be well. Michael Osodi Unit 20: Managing a Business Project or Event ...read more.

The above preview is unformatted text

This student written piece of work is one of many that can be found in our AS and A Level People & Operations Management section.

Found what you're looking for?

  • Start learning 29% faster today
  • 150,000+ documents available
  • Just £6.99 a month

Not the one? Search for your essay title...
  • Join over 1.2 million students every month
  • Accelerate your learning by 29%
  • Unlimited access from just £6.99 per month

See related essaysSee related essays

Related AS and A Level People & Operations Management essays

  1. The main aim of this research is to evaluate the information on the human ...

    The employee's needs to be provided that they are strategically made the center of attraction by the human resource (Becker and Huselid, 2001). Every aspect of the human resource function such as from employing, giving rewards, reviews, training etc., is to be enhanced so that the human capital in the organization is increased.

  2. Unit 13 - Organising an Event

    and accommodation is 'fit for purpose' and that it is at a satisfactory standard. * To provide the event at a satisfactory price which students can afford, this is arranging a suitable trip that is at a reasonable price considering the things that are included in the trip.

  1. Unit 13 Applied Business

    Therefore it was unnecessary for our Christmas Fair to need any license. * Insurance When organisers are staging events it is important that relevant insurance is taken out as it makes it possible to get financial compensation if something is to go wrong.

  2. I will be researching and managing a variety of resources. The three main types ...

    Also an employee is allowed to work longer than 48 hours a week if they agree with their employer. Because I will own the business with my partner I will not need to abide by these regulations as I am not employing anyone else.

  1. Human Resources

    There are numerous areas of the bank a branch manager has to manage, and ensure that the Bank is running smoothly and correctly on a day-to-day basis. Their role also requires them to head a team of staff, ranging of various positions in the bank, to communicate with staff on

  2. what is marketing and John Lewis Marketing

    * Durability- The ability of product to resist any fault. * Features- Characteristics of a product or service. * Quality-the characteristics of a product or service that bear on its ability to satisfy stated or implied needs. John Lewis's dedicated Merchandise Standards department works with their buying teams to make

  1. Health and safety in construction. Designers shouldnt commence work on a project unless ...

    Every contractor shall ensure that any contractor whom he appoints or engages in his turn in connection with a project is informed of the minimum amount of time which will be allowed to him for planning and preparation before he begins construction work.

  2. Motivation within a workplace - examples from Asda.

    All these factors again make the share strategy a little less motivating for the staff. One alternative strategy would be to get rid of ?buy as you earn scheme and only provide employees with ?share success? and ?save as you earn scheme.

  • Over 160,000 pieces
    of student written work
  • Annotated by
    experienced teachers
  • Ideas and feedback to
    improve your own work