Managerial Environment - Ryan office products.

Authors Avatar

BLACKBURN BUSINESS SCHOOL

DMS

MANAGERIAL ENVIRONMENT YEAR 1 ASSINGMENT

RYAN OFFICE PRODUCTS

Issue One

Bracken Ltd is threatening Ryan office products with legal action due to a delivery date not being met. This problem was due to strike action at Ryan’s French suppliers. Bracken was forced to source elsewhere at short notice and at considerable expense. Bracken are claiming they are entitled to compensation for the extra cost. The contract was on Ryan’s terms and conditions of trade.

In the terms and conditions (Ryan office products,2002) there is a force majeure clause, that reads:

14. The performance of all contracts is subject to any act of God, War, Strike, Lock-out, Fire, Flood, Drought, Tempest or any other cause beyond the control of the Firm and the Firm shall not be held responsible for failure to deliver or comply with a contract due to any such contingency.

If there is a problem outside the control of either party then this may cause frustration. Frustration is one of those legal “patches” that has evolved over the years in attempts by the courts to ensure that the framework of contract law remains adequate to satisfy that framework’s commercial reason for existing. A contract that becomes illegal to perform will be frustrated; also delays outside the control of the parties may cause frustration, if as a result performance then becomes radically different, or if the contract is deprived of its commercial purpose. A contract will not be regarded as frustrated if it simply becomes more difficult or expensive to perform; or if there is already an express term in the contract covering the contingency which has occurred; or where the event was a foreseeable part of the normal risk that party would expect to carry; or if the event was self-induced by the party seeking to rely on it.

So, what actually is a “force majeure” clause and where does it fit in when a contract becomes frustrated? Force majeure is a term borrowed from French law. There is not any precise meaning under English law (Sinclair, 2001) for the expression – it is simply a shorthand way of describing the kind of contractual term intended to give a party some relief, on the happening of an event beyond the party’s control. The relief may be a complete “get out” from the contract, or a right to suspend, or to an extension of time – it all depends on what the clause itself says. As is the rule, it’s open to the parties to negotiate and agree whatever terms they are willing to agree. If an “event” happens, then the party seeking to take advantage of the term has to prove not only that what has occurred was one of the events the term itself provided for, but also that their non-performance was a result of circumstances beyond their control, and that there were no reasonable steps they could have taken to mitigate the event or its consequences.

 Provided the force majeure clause is clearly drafted, courts will generally enforce it

according to its terms. While courts will read such a clause in light of the entire contract, the specific wording of the force majeure clause is central to any interpretation the courts put on it.

The force majeure clause in the terms and conditions states that the performance of all contracts is subject to strike, etc or any other cause beyond the control of the firm. It states that the firm shall not be held responsible for the failure to deliver or comply with a contract due to any such contingency. The strike was at the French supplier’s plant, leaving the cause even further beyond the control of the firm.

The contract was on Ryan’s terms; therefore this clause would excuse Ryan from meeting the agreed delivery date. Therefore Bracken would not be entitled to the extra cost of sourcing elsewhere.

Issue Two

Ryan has entered into an agreement with Berkamp, a Dutch manufacturer of designer desks. The agreement ensures that Ryan are the sole supplier in the UK. It also provides for a fixed resale price. Ryan has also agreed not to supply to customers resident in other member states since Berkamp has established a supplier network across the EU. Berkamp has entered into identical arrangements with one supplier in each member state. Berkamp has received written assurances from these suppliers that they will not supply to UK customers.

Before entering into such an agreement there are certain rules which apply to EU and UK competition law which must be acknowledged. The EU and UK rules both impose strict control on agreements which restrict competition in the EU and have an effect on trade between EU Member States. The UK rules apply to arrangements which affect competition and trade in the UK. Both sets of rules apply not only to blatantly anti-competitive agreements or arrangements involving price fixing or market sharing, but also to many common business arrangements such as distribution and agency agreements. Other EU countries have their own national competition laws, which may need to be considered, in relation to having transactions having a connection with them.

Join now!

Article 81 of the EC treaty (Europa, 2002) prohibits all agreements between undertakings, decisions by associations of undertakings and concerted practices which may affect trade between Member States and which have as their object or effect the prevention, restriction or distortion of competition within the Common Market, and in particular those which:

  1. directly or indirectly fix purchase or selling prices or any other trading conditions;
  2. limit or control production, markets, technical development, or investment;
  3. share markets or resources of supply;
  4. apply dissimilar conditions to equivalent transactions with other trading parties, there by placing them at a competitive disadvantage;
  5. ...

This is a preview of the whole essay