Project Management strategic issues

Authors Avatar by mad123 (student)

HERIOT – WATT UNIVERSITY

SCHOOL OF THE BUILT ENVIRONMENT

ACADEMIC CITY

DUBAI

UAE

MSc/PG Diploma

2011-2012

Project Management Strategic Issues

[D31PS]

Submitted by Palanichamy, Madhumathi – reg. No. 111687000

[Words counted – 3,500 excluding references]

Contents

Introduction…………………………………………………………………………………...        3

Project Brief………………………………………………………………………………….        3

Plot and project areas…………………………………………………………………..        4

Early Cost estimates……………………………………………………………………        4

Organisation showing related stakeholders………………………………………….        4

Responsibilities of Client representative and consultant…………………………..        5

Project Key events………………………………………………………………………        5

Time Delays and Cost Overruns………………………………………………………….        6

Time Delays………………………………………………………………………………        6

Cost Overruns……………………………………………………………………………        7

Relationship between Project Manager and Time Delays and Cost Overruns……        8

Lack of well defined roles……………………………………………………………….        8

Project Communication Hierarchy……………………………………………………..        8

Ineffective methods of Tender Bid and Analysis process………………………….        8

Poor Design Management and Sub-contractor Selection…………………………..        9

Environmental issues- Metro works……………………………………………………        9

Inaccurate Estimation and contractor Billing  Issues……………………………….        9

Poor Supervision………………………………………………………………………..        9

Design Feasibility……………………………………………………………………….        9

Analysis of Strategic and Operational PM Actions for Successful Delivery…….        10

Project team communication Protocol………………………………………………..        10

Design and Procurement Management………………………………………………        10

Appointment of effective technical and supervision team…………………………..        10

Knowledge about surrounding developments……………………………………….        10

Other PM actions………………………………………………………………………..        11

Conclusion and Lessons Learnt………………………………………………………….        11

References…………………………………………………………………………………….        12

Introduction

Delays and over budget are inevitable in construction industry irrespective of the type and complexity of the project undertaken which could be contributed due to ineffective project management among other factors.

Project Management is the “The art of directing and coordinating human and material resources throughout the life of the project………… to achieve predetermined objectives of scope, cost, time, quality and participant satisfaction” (PMI). The highlighted key words are the critical factors which determine the success of the project. It has to be kept in mind that too much focus on one factor can lead to compromise on the remaining which can in turn lead to undesirable outcomes. In addition though “Participant satisfaction” mainly implies on client satisfaction, in ideal project management system it is preferable to aim for cooperation from other stakeholders in order for smooth closeout of the project.

The objective of this report is to analyze a project in terms of project manager’s role in finding the right balance between these key factors for successful project.

Project Brief

The project was envisioned to provide a commercial /office building in prime location opposite Deira city center. It consists of G+10 building and the requirements were to provide showrooms in the ground floor and offices in the floors above along with necessary underground parking as per the local regulations (estimated and provided in three basements). The key feature of the building was the full 10 storey height atrium flanked by two office blocks on either side. The glass façade of the atrium was to allow full view of the interior of the building with its panoramic lifts catering to the office blocks.

 

Plot and Project areas

Plot area                                 3993 sq.mt..

Show rooms area                        3993 sq.mt.

Office area                                9024 sq.mt.

No. of showrooms/shops                        10

No. of offices                                        71

Total built- up designed  is 36,000 sq.mt.

Early Cost Estimates

The initial estimate of the project considering three basements was Dhs. 79 million and later was modified Dhs. 91 million when additional basement was added into the design as per client’s requirement.

Join now!

Organisation chart showing related stakeholders

Client Representative

Representative

Consultant

Project Architect/Project Manager

Site Supervision team

Main Contractor

QS Consultant

MEP Consultant

MEP Contractor (Sub- Contractor)

Shoring Contractor (Sub-Contractor)

                                                                                             

Aluminium ...

This is a preview of the whole essay