| Page


Table of Contents

Executive Summary

The ‘Blue Zuma’ is the code name for a project to develop new razor scooter to meet the growing demand for racing scooters. The project is scheduled to start on 1/2/2008 and is constrained to finish on 2/1/2009, within an estimated budget of $1.3 million.

During the initial schedule planning phase, the project was estimated to be completed by 12/22/2008, taking a total of 250 days to complete. There was only one critical path for this schedule and the non-critical activities had a significant amount of slack. Thus, the network was not very sensitive. The start of detailed product design and finish of finalized product design have been suggested as possible milestones for the project.

However, since the project is resource constrained, adding resources to the schedule table led to the over-allocation of resources. The resources Marketing Specialist, Design Engineer, Industrial Engineer and purchasing agent were over-allocated, and   activities that involved over-allocated resources were Product Design, Manufacturing Study, Detailed Marketing Plan, Manufacturing Process, Detailed Product Design, Order Components, Order Production Equipment and Install Production Equipment. An effort was made to resolve the over-allocation of resources by leveling within slack, and though this resolved the over-allocation for marketing specialist and purchasing agent, design engineer and industrial engineer were still over-allocated. Also, the sensitivity of the network had increased due to reduction in slack of non-critical activities. Upon undoing the leveling, though the problem of over-allocation was resolved, the project duration was extended to 290 days, the finish date of the project being moved to 2/19/2009.

To meet the project finish deadline of 2/1/2009, a few additional resources were allocated for specific activities. However, all of these resources were not required to reduce the duration of the project. Selected resources were allocated to specific activities to get the finish date of the project within the final finish date of the project. As a result of this allocation of resources, the project was scheduled to take 274 days and finish on 1/29/2009. This allocation of additional resources increased the sensitivity of the network very slightly.

After this revised planning, the project was estimated to cost $1,255,787. Detailed product design activity was estimated to cost the most at $317,000, and resource Design Engineer commanded a maximum total cost of $401,040. Highest cost was expected to occur in the month of July 2008, which was $171,480, and lowest cost was expected to occur in the month of October, and it amounted to $8,267. These cost estimates did not include operating costs such as utilities and costs involved in risk contingency measures.

Join now!

The risk management plan has been developed for the project after studying past projects of similar magnitude and contingency plans have been devised to mitigate the impact on project in case the event actually occurs. A risk assessment matrix has been developed and provided in this plan.  

 Project Objective and Description

The objective of this project is to develop the new razor scooter code named “Blue Zuma”. This code will be used in the future productions of racing scooters. The project must be completed by 1st February, 2009 and the project cost is expected to be less than ...

This is a preview of the whole essay