An explanation of the overhead absorption process, why it is necessary, and why different methods can give different product costs

 

Because they are common to many products, a means of sharing costs between products (absorbing) is needed

This is so that the full manufacturing costs of products can be found for stock valuation, pricing and decision-making.

This can be carried out using a single average rate per hour (labour or machine hour) for the whole factory (Plantwide rate) but this is inaccurate as it does not take account of the different uses which products make of the factory’s resources when it goes through different departments.

To obtain more accurate product costs, the traditional method was to calculate departmental rates, which take account of the different costs in different departments.

Because some departments are labour-intensive and some are machine-intensive, this approach allows the use of a labour hour rate or machine hour rate as appropriate.

By applying these rates, the product is charged the appropriate cost for each department, by applying a departmental rate, which reflects the cost of the department and the nature of the production process, and taking into account the time spent by the product in each department.

This gives more accurate cost than the cost arrived at using a Plantwide rate.

 

Comments on the calculations

 

The plantwide rate currently used is £10 per labour hour (see Appendix 1). This means that each product is given a share of the production overheads, which is proportional to the number of labour hours taken to produce it in total, in both departments. However, this does not take into account the fact that Department B is more costly than Department A, and that it has more machine hours than labour hours, which indicates that production takes place using machinery not direct labour. Therefore it would be more accurate to find a rate for each department., using a rate per direct labour hour for Department A and a rate per machine hour for Department B.

 

Before a rate can be calculated for Departments A and B, the costs of the service departments must be shared between them. There are many methods, which could be used to do this.

The simplest is the Direct method, which shares the cost of each service department between the Production departments only, and ignores the fact that service departments may provide a service to each other.

The Step method is a more accurate method of sharing the costs of service departments, which takes account of the services provided by one Service department to other departments. It does this by allocating the costs of each service department in turn between all other departments, whether Production or Service. However, once a service department’s costs have been allocated, that department is “closed” and would not receive any share of the costs of department costs subsequently allocated.

 

Departmental rates calculated using these methods were as follows (see Appendices 2 and 3 for details of the calculations):

 

 

 

The two methods have resulted in similar rates, and show that the production time  (measured by labour hours) spent by products in Department A costs much less than the time spent in Department B (measured by a machine hour rate).

Join now!

 

Applying the three rates calculated above to the time spent by the products in production gives the following results:

 

 

Comparing the figures arrived at using a Plantwide rate with those arrived at using a departmental rate, Job X costs have decreased and Job Y costs have increased. This is because Job X spends a large part of its production time in the low cost Department A (5,000 labour hours in A compared to 500 machine hours in B). In contrast, Job Y spend most of the production time in the high cost Department B (3,000 machine hours ...

This is a preview of the whole essay