DEFINITION OF FRUSTRATION

‘Discharge’ is the technical name for bringing contractual relations to an end. A contract can be discharged in one of four ways.  The main one being Frustration.

‘Frustration’ is an event which occurs outside the parties’ control which prevents the contract from being carried out.

If the injured party chooses to affirm, then the contract continues in force and the injured party awaits performance on the performance date.  This does not mean that the damages will be recoverable by the injured party due to the fact that the guilty party does not perform on the performance date.  

The injured party can then seek damages for this actual breach of contract, subject to there being no subsequent breaches to the contract.  

The following cases are examples of discharge for breach of contracts through frustration.

If the contract is frustrated between the date of affirmation and the fixed date for performance, then the injured party will lose their right to remedies for the breach.

Avery v Bowden (1855) 5 E & B 714; 119 ER 647 (QB) affirmed Exchequer Chamber (1856) 6 E & B 953

A ship was required to load a cargo at Odessa within 45 days.  The ship’s master was informed before the expiry of the laydays that no cargo would be available.  However, the master decided to stay at the port and wait for a cargo to be loaded.

 Before the 45 days were up the contract was frustrated by the outbreak of war, thus making it illegal to load a cargo at an enemy port.  

The case was held as the ship owners could not recover any damages for the anticipatory breach in failing to provide a cargo as the ship’s master had confirmed.  Where as if the master had sailed the ship away upon receiving the information, the cargo could have been loaded at a friendly port and the ship owner would have the right to claim damages for loss caused by the breach.

Sometimes it is possible for the injured party to continue with the contract and then claim the contract price rather than suing for damages for the breach.  This happened in the following case of

White & Carter (Councils) Ltd v McGregor (1962) AC 413 (HL)

A contract had been agreed between the two parties that the respondents’ business could be advertised on litter bins which were to be supplied by the local authorities for a three year period.  On the same day the contract was drawn up the defendant requested that the agreement was to be cancelled, but the plaintiffs refused to do so. The plaintiffs then displayed the adverts for 156 weeks and then claimed the contract price of £196 4s.

Lords Reid said of this case ‘If one party to a contract repudiates it in the sense of making it clear to the other party that he refuses or will refuse to carry out his part of the contract, the other party, the innocent party, has an option.  He may accept that repudiation and sue for damages for breach of contract, whether or not the time for performance has come; or he may if he chooses disregard or refuse to accept it and then the contract remains in full effect……’

A similar case is Pancahud Freres SA v Establissments General Grain Co (1970) 1 Lloyd’s Rep 53.

With this case the innocent party elected to affirm their contract after an anticipatory breach by the other party.  This meant that they were not released from obligation from tendering further performance of their own obligations under the contract.  Due to this, the repudiating party could escape liability if the affirming party was subsequently in breach of the contract.

Not all instances of anticipatory breach will amount to repudiation.  It all depends on the individual circumstances of the case.  In the case of Mersey Steel v Naylor Benson (1884) 9 App Cas 434, Lord Selborne stated ‘you must examine what (the) conduct is to see whether it amounts to renunciation, to an absolute refusal to perform the contract and whether the other party may accept it as a reason for not performing his part’

When trying to determine if the conduct does actually amount to repudiation, it is very difficult to do so.  This has been illustrated by two decisions made at the House of Lords in the following cases.

Federal Commerce & Navigation v Molena Alpha (1979) AC 757

In clause 9 of the charter it provided details that the charterers were to sign bills of lading stating that the freight had been correctly paid for.  After a dispute had arisen, with regards to deductions made by the charterers, the ship owners withdrew authority, contrary to the terms of the charter.  The master was also instructed not to sign bills of lading with the indorsement which gave the owners a lien over the cargo for freight.  By taking this action, it meant that the charterers were put in an awkward position commercially.  

The charterers treated the owner’s actions as a repudiation of the charter.  The result of the case was that it was held.  Although the term which was broken was not a condition, the breach went right to the root of the contract by depriving the charterers of virtually the whole of the benefits of the contract because the issue of such bills was essential to the charterer’s trade.

Woodar Investment Development Ltd v Wimpey Construction UK Ltd (1980) 1 WLR 277

Wimpey construction had contracted to buy a piece of land for £850,000 and had agreed to pay £150,000 upon completion to a third party, Transworld Trade Ltd.  The contract allowed the purchaser to rescind the contract if before completion a statutory authority ‘shall have commenced’ to acquire the property by compulsory purchase.  

At the date of the contract both parties knew that a draft compulsory purchase order had been made.  

Wimpey purported to terminate the contract relying on this provision, and Woodar sought damages alleging that this amounted to a wrongful repudiation.  Their damages included the loss suffered by the third party.

The House of Lords held, by a majority of 3:2, that in order to constitute a renunciation of the contract there had to be an intention to abandon the contract. Instead of abandoning the contract Wimpey were relying on its terms as justifying their right to terminate.  

Similar cases where the breach of contract was by frustration through repudiation are as follows;

Join now!

  • Jackson v Horizon Holidays Ltd (1975) 1 WLR 1468
  • New Zealand Shipping Co. Ltd v A.M. Satterthwaite & Co (1975) AC 154, 167
  • Beswick v Beswick (1968) AC 58
  • Linden Gardens Trust Ltd v Lenesta Sludge Disposals Ltd (1994) 1 AC 85
  • Darlington Borough Council v Wiltshier Northern ltd (1995) 1 WLR 68 (CA)
  • Alfred McAlpine Construction Ltd v Panatown Ltd (No.1) (2001) 1 AC 518; (2000) 3 WLR 946 (HL)

A contract is deemed to be frustrated when it is deemed impossible to perform; however frustration should not be confused with initial impossibility, which may ...

This is a preview of the whole essay