1.0 Introduction :

How a national iconic project turned into a hugely expensive and politically embarrassing fiasco?

This report intends to answer this question by  analyzing the reasons  that led to delay and cost over run in construction of new Scottish Parliament Building . This report has utilized    he researches available on the internet, auditors report and other articles  available from varied sources. As instructed, no direct contact has been made to any organization involved in the project  This report will start by introduction to the background of Scottish Parliament project and will continue by discussing the reason for delays and cost increases, role of the project management, strategic issues and at the end concluding the lessons learned  from this project. The reason for selection of this project is that  the Scottish Parliament  building was estimated  to be completed in  £ 40 m but  finished at over £400 m which is  an interesting parameter to study.

 

Fig1. Scottish Parliament Complex at Holyrood.

2.0 Background to the Scottish Parliament Project :

After the referendum in 1997, Scottish parliament was established by Scotland Act 1998 as a devolved legislature. Following this, Donald Dewar, Secretary of State of Scotland decided to have a purpose built facility to house the Parliament in the city of Edinburgh.

After having a turbulent journey to completion, Scottish parliament Complex  was formally opened by Queen Elizabeth II   on 9th October 2004.  Striking features of the complex comprise of leaf-shaped buildings, turned over boat shaped roof, a grass-roofed branch merging into adjacent parkland and gabion walls formed from the stones of previous buildings. Throughout the building there are many repeated motifs

Scottish parliament is not one building but a complex comprising of new and old buildings such as Canon gate building, Debating chamber, Dewar room , Garden Lobby, Main Hall, Media tower, MSP building ,Queensberry House and Tower Building. All of these building were constructed or renovated according to Architect’s vision (Fraser 2004). High end materials like Granite, Cattiness Stone, Oak Timber , Sycamore Timber, Steel Glass and Marble was used in the construction. Detailed Environment and sustainability study was carried out which confirmed that propose built  complex is environment friendly.  

3.0 Project History: Road to Holyrood.

3.1 Site Selection:

To begin with, Edinburgh City Council provided a long list of 27 sites in Edinburgh. In September 1997 officials short listed   three leading options: two new build

options,  either at Leith or Haymarket, or adapting and developing the existing

St Andrews House building (old Royal high school). At this stage , on 23 September the Scottish Office appointed Jones Lang Wootton, Chartered Surveyors to assist in assessing the acquisition costs and potential difficulties of the candidate sites from a commercial perspective. Assessments of traffic and environmental issues were also undertaken at this time. Haymarket was never considered as preferred option and officials  sensed real hostility in Edinburgh to the Parliament being located anywhere other than centrally thus reducing the chances of Leith.

The Holyrood site was not considered at this stage as it was  occupied by Scottish and Newcastle brewery and was anticipated that it would not be ready within the required timescale. However, an accidental meeting of a civil servant on train with an official of Newcastle and subsequent  negotiations resulted in the company indicating that they would be able to vacate the site in early 1999. As a consequence, on  8th  December 1997 an announcement was made that Holyrood would be added to the short-list and design and cost feasibility studies undertaken.

 DLE , Cost Consultants were commissioned to provide initial cost estimate for proposed sites and in January 1998 the Holyrood site was selected from the shortlist based on the following cost estimate.  

Table 1.1  Holyrood Cost Estimate.

3.2Design Selection :

Once, the location was finalized  the Scottish Office announced an international competition to find a designer for a new building to house the parliament through a competitive selection procedure . The competition itself was duly launched with a press release on 26 January 1998. giving the Project cost as being in the region of £50 million excluding VAT .

The final design teams named on 7th May 1998 ..

  A design committee was appointed under the chairmanship of Dewar to choose from a shortlist of designer. Conceptual designs were costed and displayed for public to view and provide their opinion. Feedback from the public showed that the designs of Catalan architect Enric Miralles were amongst the most popular. The design team took account of public opinion on the designs, On 6 July 1998, it was declared that the design of Enric Miralles was chosen, with work being awarded to EMBT/RMJM (Scotland) Ltd, a Spanish Scottish joint venture design company, specifically created for the project. Construction management system of procurement was adopted and BLL was appointed as construction manager.

Join now!

Construction commenced in June 1999, with the demolition of the Scottish and Newcastle brewery and the beginning of foundation work .

3.3 Journey of Estimate: The construction of the Scottish Parliament Complex   generated controversy in several aspects. Spiraling costs and the use of public money to fund the project generated most controversy. By completion, in  2004, the estimated final cost of the project was set at £430m, some ten times higher. In my opinion it is not fair to compare final figure with initial figure of £10m as it was never an estimated price but an indicative one .

...

This is a preview of the whole essay