Project Time Management (Schedule Development)In this report Ill be discussing the process of schedule development. The project schedule is the roadmap for how the project will be executed and it determines the start and finish dates of the project act

Authors Avatar

TABLE OF CONTENTS

1        Introduction…………………………………………………………        ..        2

2        Inputs…………………………………………………………………        3

2.1 Activity Lists…………………………………….……….        3

        2.2 Activity Attributes………………………………………..        3

2.3 Project Schedule Network Diagram……………………...        4

2.4 Activity Resource Requirements…………………………        4

2.5 Resource Calendars………………………………………        4

2.6 Activity Duration Estimates………………………………        4

2.7 Project Scope Statement………………………………….        4

2.8 Enterprise Environmental Factors………………………..        4

2.9 Organizational Process Assets…………………………….        4

3        Tools and Techniques…………………………………………………        5

3.1 Schedule Network Analysis……………………………….        5

3.2 Critical Path Method………………………………………        5

3.3 PERT………………………………………………………        6        

3.4 Critical Chain Method…………………………………….        7

3.5 Resource Leveling………………………………………...        7

3.6 What-if Scenario Analysis………………………………..        7

3.7 Applying Leads and Lags………………………………....        7

3.8 Schedule Compression………...…………………………..        8

4        Outputs………………………………………………………………..        8

4.1 Project Schedule…………………………………………..        8

4.1.1 Bar Chart ……….…………………………………..        8

4.1.2 Milestone Chart……………………………………...        10

4.1.3 Gantt Chart….………………………………………        10

4.1.4 Network Diagram…………………………………..        11

4.2 Schedule Baseline………………………………………...        12

4.3 Schedule Data…………………………………………….        12

4.4 Project Documents Update……………………………….        12

5        Summary………………………………………………………………        12

6        References…………………………………………………………….        12


1) Introduction:

One of the main nine project management areas is project time management which manages the timely completion of the project. Project time management is the process of:

  1. Defining project activities;
  2. Sequencing activities;
  3. Estimating activity resources;
  4. Estimating activity duration;
  5. Developing schedule;
  6. Controlling schedule.

In this report I’ll be discussing the process of schedule development. The project schedule is the roadmap for how the project will be executed and it determines the start and finish dates of the project activities.  Schedules are an important part of any project as they provide the project team, sponsor, and stakeholders a picture of the project’s status at any given time. Project scheduling is concerned with the techniques that can be employed to manage the activities that need to be undertaken during the development of a project. Scheduling is carried out in advance of the project commencing and involves:

  • Identifying the tasks that need to be carried out;
  • Estimating how long they will take;
  • Allocating resources;
  • Scheduling when the tasks will occur.

The following are the components that we must consider in developing a project schedule:

      Inputs                        Tools & Techniques                      Output        


2) Inputs        

There are several types of inputs to create a project schedule:

  • Personal and project calendars – understanding working days, shifts, and resource availability is critical to completing a project schedule.
  • Description of project scope – determining key start and end dates, major assumptions behind the plan, and key constraints and restrictions.
  • Project risks – understanding assure there's enough extra time to deal with identified risks – and with unidentified risks.
  • Lists of activities and resource requirements – determining if there are other constraints to consider when developing the schedule.
  • Understanding the resource capabilities and experience available – as well as company holidays and staff vacations – will affect the schedule.
Join now!

        

2.1 Activity lists

The activity list is essentially an itemized documentation of all of the schedule activities that are part of a particular project. These lists are typically very detailed and comprehensive, providing as many details as possible to make it as easy and quick as possible for a user to attain general, broad sheet information. Some specific categories of information that should be included within the activity list can include the title or brief description of the activity, the detailed description of the activity, the unique activity identifier, a list of project team members who may ...

This is a preview of the whole essay