This project examines the project scheduling of a contract to supply a portal frame steel building to be done by Engineering & Construction Incorporated.

Authors Avatar

TABLE OF CONTENTS

EXECUTIVE SUMMARY                                                                2

INTRODUCTION                                                                        3

BACKGROUND                                                                        5

        Abridged History Of Companies Involved                                        5

        Rose Hall Estate                                                                6

METHODOLOGY                                                                        8

        PERT / CPM Method                                                        8

        Charting                                                                        9

ANALYSIS

        Expected Times & Variances                                                10

        Comments On Task Times                                                        11

        Project Network                                                                13

        Activity Schedule                                                                14

        Variability Analysis                                                                15

        Time / Cost Analysis                                                                16

FINDINGS / RESULTS

        List Of Findings                                                                17

        Critical Path / Time Discussion                                                18

RECOMMENDATIONS                                                                20

REFERENCES                                                                        22

APPENDICIES                                                                        23

        Contract Documents                                                                23

        Corporate Documents                                                        28


EXECUTIVE SUMMARY

This project examines the project scheduling of a contract to supply a portal frame steel building to be done by Engineering & Construction Incorporated. This turnkey operation encompasses the entirety of the project, from the purchase of the raw materials to the delivery and erection of the finished product on site.

The project was evaluated using the program evaluation and review technique (PERT) and the critical path method (CPM.)

The analysis found that the expected total project time would be 290.9 days and time required for 95% probability of paying no liquidated damages is 314.2 days. The contract time for the project was 291 days, including time variations requested by the contractor (ECI.) This resulted in a shortfall of 23 days.

A time cost analysis found that the per day cost of crashing the project exceeded the per day cost of liquidated damages. So the recommendation given was to accept the liquidated damages for 23 day, which was calculated to be $955,000. It is important to note that there is a fifty percent chance the project will finish on or before the contract deadline.

The Board accepted this recommendation for the reasons above along with the knowledge that the cost savings on the steel with longer delivery times was greater than the total liquidated damages.


INTRODUCTION

Engineering & Construction Incorporated (ECI) of Guyana South America, specializes in the design, fabrication and installation of heavy metal structures. In mid 2002, ECI bid for the supply of a building to replace the Rose Hall Sugar Estate Mill House. The Rose Hall Estate is operated by the Guyana Sugar Corporation (Guysuco), which solicited and evaluated the bid.

Approval was granted for the project in September of 2002. However, due to budgetary constraints the project was placed on hold by Guysuco until January of 2003, when the contract was signed.

The project was immediately delayed due to the volatility of the steel market. The large steel members were originally slated to come from The United States. In the four months since the bid, the price of North American Steel had risen thirty percent. The bid price is fixed after it is approved. In order to maintain profitability, steel was ordered from Eastern Europe at a price equivalent to the original quote the bid was based on. Additionally, for similar reasons, steel fasteners originally ordered from North America, were sourced from China. A sixty day time variation was requested by ECI in order to accommodate this delay. At present Guysuco has given verbal approval of the variation, but no written verification has been received. The analysis assumes that the variation has been granted.

Join now!

This project will involve ordering the large steel members from Eastern Europe, fasteners from The Far East, and welding materials and consumables from North America, and shipping these to the fabrication plant just outside of Georgetown Guyana. In the plant, the raw steel members will be fabricated to form the portal frame, and then partially assembled for inspection by The Employer (Guysuco) as a condition of the contract.

Once the building is complete and inspected, it will be transported across two rivers with no bridge access, which would require in country barging of ...

This is a preview of the whole essay