Constructing a House

This project is about constructing a new home, as the title states.

The Problem

The problems are the whole project needs to be split into a series of activities (some need to be carried out simultaneously), each activity requires a certain amount of time to complete and the number of workers required to complete the activity on time in order to complete the whole project on time without any delays.

The project can only be completed on time if:

* There are sufficient resources

* There are sufficient number of workers

* The workers are multi skilled

The project is split into 41 activities.

Activity A - Purchase land

* No. of workers required - 1

* Duration - 2 days

* Precedence - N/A

This is because 1 person is required to discuss the sale of a suitable plot of land. It also requires 2 days to complete the sale of the plot of land; 1 day to discuss the choices of plots of land and another to agree on a sale and process the order. The processing takes a few hours by sending the order from the sales office to the sales headquarters, where they have other orders to process, and then sending the information back to the sales office, confirming that the land is sold. This activity must be carried out with activity B (below).

Activity B - Design house

* No. of workers required - 4

* Duration - 4 days

* Precedence - N/A

This is because 4 people are required to each plan and draw their own designs of the house. Then they decide which design is the best out of all of the designs. This takes place over 3 days. The final design is drawn carefully on the final day of the activity. This activity must be carried out with activity A (above).

Activity C - Seek planning permission

* No. of workers required - 1

* Duration - 3 days

* Precedence - A and B

This is because 1 person is required to present the final design to the council at the nearest town hall to the site. This takes place over 3 days as the councillors need to discuss the factors which make the construction of the design legal. Then the representative informs the person who presented the design whether the construction of the house is allowed to go head or not. By law, all building designs must be submitted to the council to determine whether the construction of each of the designs is legal or not. If the building is illegally constructed, the owner of the property is forced to demolish it within 12 months, or else face fines or court charges. This activity is carried out after A and B has been carried out.

Activity D - Excavate foundations

* No. of workers required - 4

* Duration - 2 days

* Precedence - C

This is because 4 people are required to carry out the activity. They have to dig up the ground in order to lay the foundations afterwards. This takes place over 2 days. This activity is carried out simultaneously with activity E.

Activity E - Excavate drains

* No. of workers required - 3

* Duration - 2 days

* Precedence - C

This is because 3 people are required to carry out the activity. They find the nearest drain and excavate it in order to lay the drains and connect them together so rainwater can flow to the sewage plant. This takes place over 2 days. This activity is carried out simultaneously with activity D.

Activity F - Lay drains

* No. of workers required - 2

* Duration - 2 days

* Precedence - E

This is because 2 people are required to carry out the activity. They lay the new drain on the site of the house and connect it with the main drain. They also decide the path of the drain and lay the drains. Also gas pipes are laid as well. This takes place over 2 days. This activity is carried out after E has been carried out.

Activity G - Backfill drains

* No. of workers required - 2

* Duration - 1 day

* Precedence - F

This is because some parts of the drain must be exposed on the ground so rainwater can flow into the drain. The exposed parts are covered with a strong, durable metal grid. This involves covering some parts of the drain with earth or tarmac and exposing them at a certain length away from other exposed parts. This activity is carried out after F has been carried out.

Activity H - Lay foundations

* No. of workers required - 3

* Duration - 3 days

* Precedence - D

When the hole is deep enough, the foundation, consisting of concrete and chipped stones, are poured into the ground, levelled out and left dry for one day. The laying process takes two days. This activity is carried out after D has been carried out.

Activity I - Brickwork to ground floor level

* No. of workers required - 4

* Duration - 3 days

* Precedence - H

When the foundation is dry brick work can start. This goes on until the brick level reaches the top of ground floor. The brick work cannot go on up to the roof level because later on the builders will face difficulty of constructing the first floor and carrying activities associated with the first floor. This activity is carried out after H has been carried out.

Activity J - Concrete Slab

* No. of workers required - 3

* Duration - 3 days

* Precedence - G and I

This involves pouring concrete over the foundation and levelling it so it is smooth. This is because when the carpet is laid, the residents of the house feel comfortable. The concrete will dry faster since it is exposed to the atmosphere, rather than confined inside the building, causing it to dry a lot more slowly. This activity is carried out after activity G and activity I has been carried out.

Activity K - Construct wooden frame
Join now!


* No. of workers required - 5

* Duration - 4 days

* Precedence - J

This activity is concerned with constructing the first floor, door, garage and outer wall frames. This is because windows, doors and garage door can be fitted easily. Roof carpentry will be easily carried out since parts of the roof frame can fit onto the outer wall frame to relieve the stress and tension of the building. This means that the tension travels down from the roof through the walls and outer wall frame to the ground. This prevents the ...

This is a preview of the whole essay