• Join over 1.2 million students every month
  • Accelerate your learning by 29%
  • Unlimited access from just £6.99 per month
Page
  1. 1
    1
  2. 2
    2
  3. 3
    3
  4. 4
    4
  5. 5
    5
  6. 6
    6
  7. 7
    7
  8. 8
    8
  9. 9
    9
  10. 10
    10
  11. 11
    11
  12. 12
    12
  13. 13
    13
  14. 14
    14
  15. 15
    15
  16. 16
    16
  17. 17
    17
  18. 18
    18
  19. 19
    19
  20. 20
    20
  21. 21
    21
  22. 22
    22
  23. 23
    23
  24. 24
    24
  25. 25
    25
  26. 26
    26
  27. 27
    27
  28. 28
    28
  29. 29
    29
  30. 30
    30
  31. 31
    31
  32. 32
    32
  33. 33
    33

DESIGN OF A RETAINING WALL SYSTEM AS PART OF A ROAD SCHEME

Extracts from this document...

Introduction

UNIVERSITY OF NEWCASTLE UPON TYNE Department of Civil Engineering and Geosciences COURSEWORK- CIV964/CW/2005 DESIGN OF A RETAINING WALL SYSTEM AS PART OF A ROAD SCHEME BY: Mr Godwin Eton A59089203 TABLE OF CONTENTS 1.0 introduction and project brief ... ... ... ... ... ... ... 2.0 subsurface condition ... ... ... ... ... ... ... ... 3.0 laboratory and field investigations, results ... ... ... ... ... 4.0 foundation design option analysis ... .... ... ... ... ... ... 5.0 foundation type option recommenced ... ... ... ... ... ... 6.0 shallow foundation options ... ... .. ... ... ... ... ... 7.0 settlement and rates of settlements ... ... ... ... ... ... 8.0 deep foundation options ... ... ... ... ... ... ... ... 9.0 summary and recommendations ... ... ... ... ... ... ... 10.0 cost implications ... ... ... ... ... ... ... ... ... LIST OF FIGURES Figure 1: Cross-section showing the subsurface profile at the project site ... ... Figure 2: Plan view of the project site showing column spacing ... ... ... Figure 3: Schematic representation of the proposed square pad ... ... ... foundation with vertical load Figure 4: Schematic representation of the proposed of embedment of the piles along the longitudinal axis of the proposed building ... ... ... Figure 5: Penetration of single pile into the subsurface ... ... ... ... Figure 6: Load on a pile group arrangement ... ... ... ... ... ... Figure 7: Penetration of pile group into the subsurface at case #1 ... ... ... Figure 8: Pile cap over four piles to be employed at the project site ... ... ... Figure 9: Schematic representation of the settlement based on the ... ... ... equivalent raft concept... ... ... ... ... ... ... ... List of Tables Table1: Summary of geotechnical properties of the subsurface at the project site ... ...read more.

Middle

A potential slip surface was assumed to lie within the laminated clay layer hence; it was taken as the boundary between the upper and the lower soil layers. Slope analysis took place in two stages, first the stability of the existing slope was analysis and after which stability was analyzed with the retaining wall in place to assess for possibility of failure. Results from computer Run Following the above analysis, results showed that the existing slope is stable with a Factor of Safety of 4.03. For the slope with the retaining wall no failure plan was obtained below depth of 8.00 meters implying that the wall is stable at a depth of 15.00 meters of embedment. A Factor of Safety of 1.33 was obtained. Results of the computer runs are presented in figures 3 and 4 below. Figure 3: Slope Stability analysis for the Existing Slope before the emplacement of the wall Figure 4: Slope Stability analysis for the Existing Slope after the emplacement of the wall 6.0 3.0 OPTION ANAYSIS Remarks DISCUSSION IN RELATION TO THE DESIGN AND CONSTRUCTION OF THE RETAINING WALL AT THE PROJECT SITE Retaining Wall Options Analysis and Recommendation. The most common types retaining whish can be employed for the proposed project include: Gravity concrete wall, cantilever T-reinforced concrete wall, cantilever with sheet pile base and embedded wall (propped or un-propped) The stratigraphic arrangement over the whole plan area of the site, led to the early decision to use a single-propped embedded Diaphragm wall as retaining wall system to provide both temporary and permanent support. Alternative considerations were Cantilever free standing wall system, Cantilever wall system on pile foundations and gravity wall. These were quickly discarded because of cost implications, restricted access at proposed road below the wall, proposed retained height of 6.50 meters, enormous earthworks that will be involved and unfavourable subsurface conditions. Gravity wall was not considered because of height restriction of which Clayton et all (1993) ...read more.

Conclusion

Design Philosophy The limit state design philosophy is adopted and it is assumed that the design will satisfy both the ULS and SLS. Different methods are employed to calculate the Factor of Safety. Determination of Depth of Embedment The detailed calculations involved assessment of the depth of embedment at both the two axes namely the eastern and southern axes. (figure 6a) The worst case (with the thick layer of laminated clay) is considered for detailed calculations (Figure 6b). Computer runs for the western side are also included in this report. N S q kN/m2 (surcharge) = 10 kN/m2 Proposed engineering fill q Figure 6: Cross section of the Single-propped Diaphragm Wall proposed for the project site Note: The position of the prop is chosen as 3.5m below the new ground surface in order to avoid the two made grounds which are likely to reduce the prop force when installed. However, additional prop can be installed at a shallower depth for added stability of the proposed wall. 5.0 Summary And Concluding Remarks Remarks A retaining wall system involving Reinforced concrete diaphragm wall has been proposed for used as a retaining structure at the proposed project site. The wall should be installed at an embedment depth of 8.50 and 11 meters corresponding to a Factor of Safety of between 1.5 - 2.0, and a retained height of 6.50 meters. A single propped should be installed at a depth of 3.50 meters from the top of the fill level. In addition, 0.5 meter allowance was made the proposed road pavement. Summary of the calculated Factor of Safety (FoS) for the various stages of work are presented in table 4 below. Table 3: Summary of Calculated Factor of Safety Stage of work Permanent works Temporary short term Temporary long term Remarks Fos (8.5m) West East West East West East 1.9 1.5 1.8 1.2 2.0 2.2 OK Fos 11.4 m - 2.0 - - - - OK Finally, it is believed that the above findings, comments, discussions and recommendations would be of assistance in the deliberations and decisions in the process of constructing the envisaged structures. ...read more.

The above preview is unformatted text

This student written piece of work is one of many that can be found in our University Degree Engineering section.

Found what you're looking for?

  • Start learning 29% faster today
  • 150,000+ documents available
  • Just £6.99 a month

Not the one? Search for your essay title...
  • Join over 1.2 million students every month
  • Accelerate your learning by 29%
  • Unlimited access from just £6.99 per month

See related essaysSee related essays

Related University Degree Engineering essays

  1. Members of the design team and their job roles in a construction project.

    They prove that buildings can withstand the pressures of use by using mathematical calculations. In the design team, the Structural Engineer specialises in designing structures of the buildings and ensuring that they can withstand all the pressures they have to endure and they achieve this by developing initial designs, using

  2. Project Management Theory and practice

    Street Scale: Planning, Massing and Detail Design for the streetscapes and podiums of Business Bay shall respect human scale and human needs by providing a comfortable year round environment. ? City Scale: It is technically comparable to the standards found in other great cities of the world.

  1. Surface Material Choice, Environmental Considerations and Work Schedules for a Motorway widening project.

    Last accessed 2/03/2011. HSI. (2009).Project applications. Available: http://hsi-engineering.com/project_appl/pavements/index.html. Last accessed 26/02/2010. Hunter, N (1994) Bituminous mixtures in road construction, London: Thomas Telford Garber, N and Hoel, L (2009). Traffic and highway engineering. 4th ed. USA: Thomson West. 1076-1078. O'Flaherty, C.A (2002) Highways the location, design, construction and maintenance of road pavements, 4th edition, Oxford: Butterworth - Heinemann Roberts, M.

  2. 8.2 SUPERSTRUCTURE FOR MULTI-STOREY CAR PARK, UNIT 8 CIVIL ENGINEERING CONSTRUCTION A

    For larger loads outriggers are used and maximum lift is 30 tones. See (ceca14-7) Crawler cranes can be universal power unit rigged as a crane or purpose designed track mounted crane with or without fly jib attachment. Their lifting capacities is up to 45tonnes.track mounted cranes can travel and carry

  1. Floating crane design. The following report presents an over view of a floating ...

    4.268 367.5115 2.0115572 1.0057786 3.7003222 1.5734045 5.159103 143000 3470288 3613287.8 1568.52 4.258 368.327 2.0160208 1.0080104 3.7198051 1.5467039 4.798454 151000 3470288 3621287.8 1568.52 4.249 369.1425 2.0204843 1.0102422 3.739202 1.5201312 4.476048 159000 3470288 3629287.8 1568.52 4.24 369.958 2.0249479 1.012474 3.7585133 1.4936854 4.186114 167000 3470288 3637287.8 1568.52 4.23 370.7735 2.0294115 1.0147057 3.7777397 1.4673658

  2. Site Investigation Report for Holly Hill Campus, Bexley College

    Used when: o The soil is weak o Columns are so closely spaced in both directions o Overlapping isolated column foundations bearing a high load A raft reduces the ground pressure immediately. Is made up of alot of re-bar. Is an alternative to piling.

  1. End of Unit Assignment - Site Surveying

    Figure 6: Surveying for Construction, Third Edition (Page 234) A complication that is sometimes encountered when setting out curves for road construction is where the origin point is obstructed and cannot be accessed. Two methods of overcoming this obstacle are 'Plot and Transfer' and 'Calculate and Transfer'; both methods require a chord between the two tangent points of the arc.

  2. The object of this experiment is to determine the Liquid and Plastic Limits of ...

    DISCUSSION During the experiment several errors could occur. One of the basic errors is misreading the dial gauge scale for the Penetrometer test, fortunately we where briefed thoroughly about the scale from our tutor so that was avoided. The Penetrometer cone is a crucial part of the apparatus when undertaking the penetration test to work out the liquid limit.

  • Over 160,000 pieces
    of student written work
  • Annotated by
    experienced teachers
  • Ideas and feedback to
    improve your own work