Contract Law - Offer, Acceptance, Estoppel, Duress

Authors Avatar

TOGA is an electronics company specialising in games consoles. In January 2004 it entered into a contract with XENA, a specialist technology firm, for the production and delivery by the end of October 2005 of 5000 units of TOGA’s new “Y-Cube” console for the price of £1million. In August 2005 XENA informed TOGA that unless they received an immediate payment of 200,000 in addition to their original agreed fee, they might not be able to deliver the consoles on time. As TOGA needed to have the consoles ready for sales for Christmas it reluctantly agreed to pay. XENA managed to deliver the consoles on time but sales during the holidays went so badly that in January 2006 TOGA informed XENA that it would not be able to make the remaining payment of £1million. XENA fearing that TOGA might go bankrupt agreed to accept 600,000 in full settlement. Later in January XENA had a change of heart and demanded the payment of the full settlement from TOGA.

        A contract is a legally enforceable promise or an agreement. In order to establish a contract a number of preconditions must be satisfied; offer, acceptance, consideration (degree of value), certainty and intention to create legal relations. In regards to the case in question, it has already been established that a binding contract exists between TOGA and XENA. However a number of legal issues are evidently illustrated in this case. In the first part of this essay I will analyse the payment of 200,000 in addition to TOGA and XENA’s agreed fee; whether this amounts to sufficient consideration and if economic duress plays a significant part in decision making. In the second part I will consider XENA’s acceptance of 600,000 in full settlement from TOGA, and XENA’s change of heart and demand of payment of the full settlement; if part payment of debt is sufficient consideration and if promissory estoppel can be raised as a defence.

        Consideration is where each party gives something stipulated by the other as the price for his promise. Consideration in the additional payment of 200,000 to TOGA and XENA’s agreed fee is evidently questionable; performance of a duty already owed to TOGA, XENA is being contracted twice to perform its contractual obligations. According to authority in Stilk v. Myrick [1809], Lord Ellenborough held that performance of a duty already owed is not good consideration and therefore not a contractual agreement. Based on this authority it is fair to say that there is no contractual obligation for the transfer of 200,000 between TOGA and XENA, and that TOGA is entitled to bring a cause of action against TOGA in recovering this 200,000 in damages.

Join now!

However later Court of Appeal authority in Williams v. Roffey Bros. [1991] outlines this idea of practical benefit. The plaintiff, subcontracted by the defendant, got into financial difficulty and the defendant offered to pay the plaintiff an extra £575 per flat completed as main contract containing time penalty clause and were worried the work wouldn’t be completed on time. Plaintiff sued for additional sum promised and Glidewell LJ, distinguishing rule in Stilk v. Myrick, held that promise to pay extra for something already obliged to do is good consideration, but only if there is a practical benefit. TOGA would clearly ...

This is a preview of the whole essay