IT Strategy in the Criminal Justice System.

Authors Avatar

Strategic Information Planning         CM1379-3

A Report on the IT Strategy in the Criminal Justice System –

The LIBRA Project


Contents

INTRODUCTION        

Objectives        

Terms of Reference        

THE IT STRATEGY BEHIND THE LIBRA PROJECT        

Application Portfolio Model        

Stages involved in the LIBRA project        

Comparison with Earls (1989) Nine Factors        

Strategic Grid        

Justification of the plotted points on the Strategic grid        

The Index Matrix        

Justification of the plotted points on The Index Matrix        

Significant faults identified during the analysis of the LIBRA project        

THE REVISED IT STRATEGY        

Revised stages of the LIBRA project        

Strategic Grid        

Transformation Graph        

CONCLUSIONS & RECOMMENDATIONS        

Diagram 1: Flow of manual system information exchange        

Magistrates Inspectorate: Key findings of the review        

Key findings of the review        

Strategic objectives        

Key areas of performance        

Functional areas of performance        

Measurements        

Costs of collection        

Computer systems        

Weighted caseload        

Earl (1989) Nine Factors        

LINKS        

BOOKS AND JOURNALS        


Strategic Information Planning        

A Report on the IT Strategy in the Criminal Justice System – The LIBRA Project

Introduction

This report is for the attention of the Lord Chancellors Department (LCD) in relation to the IT strategy implemented in the Criminal Justice System, the LIBRA project.  

The project was originally initiated on the grounds that the existing manual computer systems for the Magistrate Courts was labour intensive, non cost effective, slow, complex and at times inaccurate due to human error.  As a consequence court ‘casework’ records had been delayed in transit, causing court hearings to be delayed, postponed or even sometimes abandoned due to irregularities in procedure resulting from documents being lost in transit.  (Appendix A: Diagram 1)

The need was apparent that a new efficient IT infrastructure and strategy was required to meet the organisations demands of electronically exchanging information such as ‘casework’ records between the Magistrate’s Courts of England and Wales.

The result of the initial analysis of the unreliable existing system meant that in 1997 the LIBRA project was scheduled for development with Private Funding Initiative (PFI) funding.  The system was intended to serve as “a national automated electronic case working and administration system to serve all of the magistrate’s courts in England and Wales”.

Objectives

The objectives of this report are based around the analysis of the current LIBRA project and resulting in recommendations being made as well as an alternative solution to be designed in response to a successful major change made by the LCD department.  

The main objectives summarised as follows:

  • an analysis of the faults in the existing IT strategy
  • recommendations for preventing these faults
  • design and develop a new IT strategy for the remaining Magistrates Court system’s to form a new template for the LIBRA system.
  • using appropriate tools and techniques for analysis and design
  • justify the appropriateness of the techniques being used

Based on the Magistrates Inspectorate (see Appendix A) the review found three strategic objectives to be common within the majority of the Magistrates Courts Committee, these were to improve:

  • efficiency and electiveness of court services
  • quality of court services for all court users
  • the value for money of the services

Terms of Reference

The outcome of the report is to illustrate to the LCD the existing faults, and prevention of these faults, of the current IT strategy on which the LIBRA project was based.  The report will also advise on a possible new IT strategy.

A recommended action plan of delivery will be the evaluation and breakdown of the LIBRA project in its current state, and to research the strategic tools and techniques to aid this evaluation.

A basic overview and the fundamental argument for applying a IT/IS strategy to this situation is due to the changing role of IT.  In this situation it is apparent that a problem needs to be resolved using a technological solution, due to an organisation, ‘pull’.

The IT Strategy Behind the LIBRA Project

Application Portfolio Model

Stages involved in the LIBRA project

The following stages have been taken from the LIBRA project case study and will be referred to in all of the analysis techniques used in this section of the report.

  1. In 1997, the LCD initiated the LIBRA project to develop a national automated electronic case working and administration system to serve all of the Magistrates Court’s in England and Wales
  2. The project was seen by the New Labour government as a way of using private investors to finance public infrastructure projects. The government started the PFI in order to gather such finance.
  3. The LIBRA project contract was awarded to ICL (later Fujitsu) for £183m.  PFI were responsible for awarding the contractors.
  4. Due to a disagreement with the LCD over delays and spiraling costs, the project came to a halt.
  5. Talks continued until 23rd July 2002.  The LCD ended the Fujitsu contract for the entire LIBRA project.  The project was sectioned into three parts.

        Fujitsu were allowed to keep the first section of the project, which involved the         development and supply of office automation hardware and software and a national         network.  They charged $49 million more than the original contract.

        The second section of the project was the supply of off-the-shelf case working         software; the third section involved integrating the software into the existing IT         systems run by the magistrate courts and the other criminal justice agencies. The         choice of contractors to carry out the work on these sections was not yet decided as         of September 2002.

        Because of the sectioning, discrepancies arose with the IT staff who where expecting         to work for Fujitsu Services with the LIBRA contract.   Until the second and third         section is contracted IT staff will be still unsure about their future.

  1. Two new court buildings were erected in Worcester and Kidderminster.  These were seen by many as “pathfinder projects” to test that these new buildings would successfully link up to the LIBRA project.   It was at this time that problems linking the IT strategy to the physical implementation were first noticed.
  2. The PFI used inappropriate contractors such as Rentokil (best known for their pest control business) who charged £550 for network sockets when at most electrical stores these sockets retailed at around £120.  However Rentokil argued that they followed LDC specifications.
  3. A study was carried out showing that three times the workstation points was needed.
  4. Additional fibre-optic data cables were installed by the original contractors, Fujitsu.  Fujitsu’s survey of the completed Kidderminster building suggested that extra cabling and power points were needed to bring the building up to LIBRA standards.
Join now!

Comparison with Earls (1989) Nine Factors

Using Earls (1989) nine factors (see Appendix A) to show that IS/IT in the LIBRA project is a strategic issue.

“IT is a high-expenditure activity”

The implementation of the IT strategy was obviously a high expenditure activity due to the vast amounts of money funded, £183m, and a further £49m to ICL (later Fujitsu).  The high expenditure rate was inevitable due to the scope of the project spanning England and Wales.

“The current economic climate favours IT”

The manual system in place was slow, labour intensive and costly and mistakes were being made during ...

This is a preview of the whole essay