Topic 6 : Remedies For Breach of Contract the Remedies Available To the Injured Party Will Depend On the Nature of the Breach Because the Results Will Defer As Between the Parties.

Authors Avatar

Topic 6 : Remedies for Breach of Contract

The remedies available to the injured party will depend on the nature of the breach because the results will defer as between the parties.

 

1. Rescission

Rescission is available for

It aims to restore the parties to the positions they were in before they entered into the contract. This means, for example, that a person who obtains goods on the basis of a misstatement of fact may only rescind the contract if they are willing and able to restore the goods they received. If this cannot be done, the remedy of rescission is lost.

 

2. Damages

The aim of an action for damages is to enable an innocent party to receive monetary compensation from the party responsible for the breach of contract. Generally, it is to put the injured party in the position that they would have occupied if the contract had been performed as was originally intended. Therefore, damages are calculated on the basis of looking at what the position should have been if the contract had been properly performed.

The types of damages that may be awarded to an injured party under a contract are  (or punishment) damages.

Four questions need to be considered when a claim is made for damages:

i. Causation

The injured party has to prove that the loss or damage that they have suffered is a result of the defendant's breach.

ii Remoteness of damage

The court will only be interested in those losses reasonably related to the contract. Was the loss suffered by the plaintiff reasonably foreseeable as a result of the breach of contract ?  suggests that the only losses that a plaintiff can recover are:

  • Those that arise from the usual or normal course of events; and
  • Those that arise from special or exceptional circumstances which the defendant knows of before entering into the contract. See, for example, . Where the damages are not foreseeable, they are considered to be too remote and the defendant will not be liable.

Case Study

Hadley v Baxendale (1854) 9 Ex 341

Facts: Hadley, a mill owner, had to stop work in the mill because of a broken crankshaft. The shaft had to be sent back to the manufacturer as a pattern had to be made for a new one. Baxendale, a carrier, promised Hadley that the crankshaft would reach the manufacturer on the following day. His negligence, however, resulted in its delay and the mill was out of commission for months longer than it should have been.

Issue: Could Hadley recover damages for loss of profit caused by the delay ? The carrier's defence was that he had no way of knowing that the delay in delivery of the shaft would cause the mill to be shutdown.

Decision: The carrier was not liable for the loss of profits caused by the delay, as the loss did not flow directly from the breach of contract. It was too remote to have been foreseen by a reasonable person.

Case Study

Victoria Laundry v Newman Industries (1949) 2 KB 528:

Facts: Newman Industries contracted to deliver a boiler to the plaintiffs. They knew that the plaintiffs required the boiler urgently to enable them to take advantage of favourable trading conditions and to undertake expansion of their business. The boiler was damaged in the course of delivery by Newman and was late in installation.

Join now!

Issues: Could the plaintiffs recover for:

  • loss of profit the laundry would have made had the boiler been delivered on time; and
  • loss of profit from the dyeing contracts ?

Decision: The court held that the laundry profits were recoverable, as the defendants must have contemplated that there would be a loss if there was a delay. However the loss on the dyeing contracts was not recoverable. The defendants were not in a position to know of the highly profitable nature of such contracts for which the plaintiff was negotiating. As a result this was not ...

This is a preview of the whole essay