Critical Path Analysis.

Authors Avatar

CRITICAL PATH ANALYSIS

Introduction

 

In projects made up of various activities where ‘time is of the essence’, the duration of each activity needs to be managed.  Certain activities run simultaneously and some must precede others.  If all activities are listed with their duration and preceding activities these can be networked visually.  Earliest and  latest times for each event (starting and finishing times for activities) can be established till the last activity. This saves time making the project as efficient as possible.   Certain activities when delayed will increase the time of the entire project.  These form a path known as the ‘critical path’ and show those ‘critical activities’ that have no spare time.  All these steps make up the Critical Path Analysis.

After analysis of the network a cascade chart can be formed with a corresponding resource histogram showing the number of workers throughout the project.  The floats can be re-arranged to produce a levelled histogram where the number of workers are levelled out throughout the project.

These are helpful in mall projects like cooking where they may only be two cooks to carry out the whole project ranging to large-scale projects like constructing a shopping centre.

I am required to cook a meal consisting of 21 activities.   This includes the preparing and clearing away of the meal.  

I am deciding to allocate ‘get ingredients’ to merely collecting of ingredients in the kitchen and not the buying.  I feel that this is unnecessary for this project and the time spent in doing this (1 hour minimum) will not be in relation to the rest of the project.

All times are from a recipe book and activities such as ‘get ingredients’, ‘serve dish’, ‘serve apple pie’, ‘eat and clean away’ were estimations through past cooking experiences.

PRECEDENCE TABLE

Join now!

Critical Activities

There are 13 critical activities.  These are ‘get ingredients’, ‘put water in the pan’, ‘cook pasta shells’, ‘drain pasta’, ‘place pasta on dish’, ‘spoon cream on pasta’, ‘place dish in oven’, ‘remove dish from oven’, ‘serve dish’, ‘eat meal’, ‘cook apple pie’, ‘serve apple pie’ and ‘eat and clean away apple pie’.

The critical activities are activities that cannot be delayed in order for the network to finish on time (at 79 ...

This is a preview of the whole essay