Critical Path Analysis.

Authors Avatar
Critical Path Analysis

When choosing a project for this piece of coursework it was important to find something that was both original and capable of meeting the coursework criteria. However, after some research into possible projects, I decided on web design. Web design is happening all over the world at current due to the increasing demand for online presence and business prospect. Most companies wanting to add a website to their business would be happy to pay out large sums of money to a web design firm that may not be meeting client deadlines in the most optimal time. Therefore, my project is aimed at a large scale website design project, trying to find the minimal time in which a website can be completed in. If successful, this project could be used by a wide range of web businesses, capable of enhancing time management and resource control, thus savings money.

One problem that I faced, almost straight away, was that websites come in many shapes and sizes. Therefore I had to narrow down the kind of site that I was working with. So, based on a web project that I recently read about, I set out to complete modeling for a 2-tier (public and members) web site, capable of offering subscriptions to users so that they could access a 'member-only' section. This involved a lot more that just a standard website as a business would have to implement different modules of programming to perform certain tasks both on the server and client-side system. In short, the project involved lots of activities that needed to be completed.

Precedence Table:

Once I had researched what activities my project entailed, I set out to find how long each activity would take, and how many team-members would be needed to complete each activity efficiently. For this, I went and spoke with a web administrator at PCS (Portcullis House) in Southend. After having spoken with PCS, I finalized a 26-activity project, with durations and team-members, for which I created a precedence table. This table shows the label for the activity, a description of the activity, its duration, which activities need to be completed for the next to be carried out (preceding activity), and finally the number of workers for each activity. The precedence table is shown in figure 1.1. From this we can see the complexity of the website being designed.
Join now!


Activity Network:

From the precedence table it was possible to produce an activity network which shows how each activity is relative to the next. Not only does this show which activities are dependant on each other, but it gives a clear layout of the project activities. Due to the many possibilities of layout when designing an activity network, it took several attempts to find a reasonable activity network layout. One such attempt is seen in figure 1.0, eventually being transformed in the final layout seen in figure 1.2.

Dummies:

Dummies have been used to ...

This is a preview of the whole essay