Risk Responses:
a) Avoid the risk:
- Avoid direct skin contact while handling mortar, used PVC gloves
- Use cement or cement containing products within the use-by date
b) Mitigate the risk:
- Conduct a talk to explained the risk of dermatitis and cement burns and precautions to be taken
- Provide washing facilities with hot and cold water supply, soap and basins large enough to wash forearms
- Training on how to treat exposure to be given to all operatives
- Be aware of anyone with early signs of dermatitis by supervisor
(Health and Safety Executive, 2008)
MICRO-EVENT 2
Weather condition. E.g.: Continuous rain
This event is categorized as not direct associated but it is predictable. The progress of the construction project is not related to the season or weather. No matter what season is it, the progress of work in construction still have to be carry on. The weather can be forecasted. It is reasonably have been foreseen by an experienced contractor.
Risk Analysis and Risk Responses:
A qualitative assessment is carried out to analyse the risk due to the inclement weather condition. This technique is used because there is no figure available from the risk to adopt quantitative analysis. The risks are identified by project personnel based on own knowledge of the previous or similar projects. (Caltrans, 2007)
MICRO-EVENT 3
Amendment on construction design due to architect favour.
E.g.: Softwood timber wall change to traditional brick wall.
This event is categorized in direct associated but not predictable. It is an important and sensitive case for the changes of a design in a project because it will directly affect the construction method and cost spent on the materials. However, it is unpredictable that the amendment of the design will be changing the whole specification of the particular elements.
Risk Identification:
Based on the structured interview meeting with a qualified professional and risk audit interviews with key staff, the risk for this event is identified. It includes involves additional cost to buy bricks and cement, recruit skilled labourers for bricklayers and termination of contract with sub-contractor.
Risk Analysis:
- Amendment of a design will only take place if an agreement is being brought upon with the client and the client is then willing to accept the likelihood of risk and impact to the project either in cost or time.
- The changes made are to improve the quality of the building with a better design as the brick wall will last longer and more worthwhile.
- A quantitative technique adopts in this event is to calculate the total cost increasing due to the price of bricks and cost of labourers.
-
Assume that the duration for erecting the wall is estimate for 90 days and the area of the wall is 1,388 m2.
- Hence, it clearly shows that the amendment of the wall will cause the contractor to pay extra amount of £ 7,492.56 for the cost.
Sensitivity Analysis is also used to evaluate the effects of the incremental changes in the values of bricks and salary for bricklayers if the prices are varied.
SensIt Spider Numerical and Chart Output
- On the spider chart above, lines that are approaching the horizontal axes where small percentage changes do not have much effect on the output value is the cost of timber.
- While the lines that are approaching 90˚ have a greater affect on the output value are the cost of bricks and the salaries for bricklayers.
Risk Responses:
- Avoid the risk
- The client should engage a more professional and experienced architect to in charge design of the project and make the best decision before choosing the type of construction and the use of the any relevant materials to avoid any argument with contractor.
b) Mitigate the risk
- Provide workshop for the labourers to teach them how to lay brick wall so that it can reduces cost to engage new group of bricklayers.
- Client is responsible to pay more on the additional cost to the contractor if the works is sure to be carried on.
c) Retention of risk
- The risk produces only a small, repetitive loss of the total cost. Hence, it is more suits to be retain where as it will cut down the problems or termination of the contract and will not affect the reputation of the contractor.
References:
-
Caltrans, 2007. Project Risk Management Handbook: Threats and Opportunities. 2nd Edition. Sacramentio. [online] Available from:
. [Accessed 7 April 2009]
-
ELLERY, S., 2008. Bricks and labour cost more in South-west. Construction News. [online] Available from:
.
[Accessed 7 April 2009]
-
Health and Safety Executive, 2008. Example risk assessment of contract bricklayer. [online] Colegate, Norwich. Health and Safety Executive. Available from:
. [Accessed 7 April 2009]
Bibliography:
-
FLANAGAN, R. and NORMAN, G., 1993. Risk Management and Construction. Oxford: Blackwell Scientific.
-
SMITH, N.J., MERNA, T., and JOBLING, P., eds., 1999. Managing Risk in Construction Projects. Oxford: Blackwell Scientific.
-
WALKER, P. and GREENWOOD, D., 2002. Construction Companion to Risk and Value Management. London: RIBA.
-
UFF, J. and ODAMS, A. M., ed., 1995. Risk, Management and Procurement in Construction. London: Centre of Construction Law and Management.