Business NPV

The NPV is £56700 for the project given the best estimate cash flows. Therefore under the assumption that the firm is operating to maximise the market value of their common stock, and under the assumed conditions of certainty of prices of all assets, the firm should accept the project, as the NPV is positive. This will increase the value of the firm as long as no other groups of projects can be found which will increase the value of the firm.

B)

The project has 2 internal rates of return (multiple IRR's) that are 4.8% and 13.45%. Affects of multiple IRR's are shown in graph 1. The discount rate exceeds 4.8% the proposal becomes positive and at 13.45% the present value of all the cash flows is 0. Therefore when the cost of capital is between 4.8% and 13.45% the NPV is positive, and following the NPV rule the project should be accepted. However if the IRR calculation of 4.8% is used the project maybe incorrectly rejected as the cost of capital is in excess of 4.8%. Graph 1 however indicates this is an incorrect decision when the cost of capital is between 4.8% and 13.45%.

C)

Both the IRR and the NPV take account of time value of money, but situations arise where the IRR method leads to different decisions being made from those that would implement the NPV method.

Mutually exclusive projects exist when there is acceptance of one project excludes the acceptance of another. The following example will illustrate how the NPV and the IRR lead to different decisions.

Initial Investment Outlay Net Inflow End Of Year (£)

1 2 3

Project A £7000 3430 3430 3430

Project B £12000 5520 5520 5520

Cost of Capital = 10%

The NPV and IRR calculations are as follows:

IRR (%) NPV (£)

Project A 22 1530

Project B 18 1728

Source: Principles of Corporate

Finance, 6th edition

Brealy and Myers

The IRR ranks A first and NPV ranks B first. If the projects were independent this would be irrelevant, since both would be accepted. However the case is mutually exclusive, therefore raking is crucial. Graph 2 illustrates this.

A discount rate greater than 12% no contradictions arise, below 12% project B has higher NPV and project A has a higher IRR. The IRR gives incorrect ranking proved by considering the increments of cash flows of project B over A.

Join now!

Years

0 1 2 3

(£) (£) (£) (£)

Project A 120005520 5520 5520

Project B 7000 3430 3430 3430

Incremental Cash Flow 5000 2090 2090 2090

If the firm did use the IRR method and chose product A, we can establish if it is worthwhile to the incremental investment (B-A). The acceptance of this investment + incremental investment = A + (B-A), this is = to accepting project B. Firm therefore accepts the incremental investment. Using the IRR rule is the same as moving from A to B. The IRR of the incremental investment is (B-A) 12%. The cost of capital is ...

This is a preview of the whole essay