Executive shirts company case. Problem Statement: There are two alternative plans in order to introduce customized shirt manufacturing in the factory.

Authors Avatar by mayankm12 (student)

Problem Statement: There are two alternative plans in order to introduce customized shirt manufacturing in the factory. In the first plan, we are looking at the option where existing line is used with addition one new machine. In the second plan we will look at the option of introducing a new line dedicated to manufacturing the customized shirts with resources drawn from main line. The main line will work with reduced resources.

Metric Definitions (& associated assumptions):

  • Bottleneck Time (Actual Cycle Time): This is the maximum cycle time in the entire process.
  • Production Capacity: Production capacity is the total manufacturing capacity of the machinery of the plant in the time the labor is normally available.
  • WIP (Work in Progress) Inventory:  This includes the entire set of unfinished items on which the workers are working.
  • Manufacturing Lead Time: Time to get all the WIP shirts to a finished state so that a new order can be fully manufactured.
  • Current Running Capacity: The number of shirts that are being manufactured with current machinery and labor.
  • Direct Labor Content: Total time spent on each shirt by all labourers excluding the 4 material handlers.
  • Direct Labor Cost: Total cost of all labor that are directly involved in the manufacturing process (we are excluding the material handlers and supervisors).
  • Direct Labor Utilization:  This is the proportion of time that labor available is utilized in the production process.

Scenario One: Current State Of Production

The bottleneck in current production scenario is the make cuffs process which is 0.5 minute per shirt (from the table 1)

Since, the process takes 0.5 0minute per shirt, therefore the production capacity for 8hrs per day = (8*60)/0.5 = 960 shirts per day

But its given 16000 regular shirts are made every month, therefore current production capacity per day = 16000/20 = 800 shirts per day

Hence, Capacity Utilisation for production = 800/960 = 83.33%

Join now!

From Exhibit 3, Work in progress Inventory = Total Inventory * batch size

                                                                               = (16+144+12+12+12)*60 = 11760 shirts

Manufacturing lead time = (WIP Inventory * Cycle time) / No. of hours in a day

                                              = (11760*0.5)/(8*60) = 12.25 ...