This report focuses on the heat recovery system which use the heat from the gas turbine exhaust gas to produce steam. e report has a detailed design of the economizer and evaporator where as the steam drum, gas stack, pumps and duct burner are discussed b

Authors Avatar

  1. Executive Summary

Civ-Chem Engineering Solutions was approached by one of the largest manufacturers of recycled paper and corrugated cardboard i.e. Smurfit Kappa to design an effluent treatment plant, on-site electricity generation system, system to provide heating in plant and a training and design facility. All of the previous are to be designed so that a second paper mill line can make use of these facilities in 5 years time. The current CHP generates 4 MW of electrical power as well as providing 20 tonne/hr of steam, this is less than the requirement of the plant which is about 8 MW of electrical power and 45 tonne/hr of steam. The plant also requires 2800 m3/day of water. Civ-Chem Engineering Solutions is to design a 4 MW CHP plant which ensures steam generation of 25 tonne/hr. Civ-Chem Engineering Solutions also have to design an effluent treatment facility which reduces the BOD and COD discharged to the foul sewer system.

This report focuses on the heat recovery system which use the heat from the gas turbine exhaust gas to produce steam. Heat recovery steam generators(HRSG) are being used more commonly now in combination with gas turbines cause they are efficient, pollution free and relatively cheaper. The design of an HRSG can be vast, so this report is focused on the more important parts of a HRSG. The report has a detailed design of the economizer and evaporator where as the steam drum, gas stack, pumps and duct burner are discussed briefly. The HRSG designed ensures production of steam at 25 tonne/hr at 198 °C and 15 bar. The report also discusses the control needed for an HRSG to ensure easy and reliable control for optimum operation. The P&ID diagram shows how this control is implemented.

The last section of the report discusses the financial side of the HRSG. The capital cost of the HRSG unit is £65100. The operating costs which includes the fixed and unfixed cost is         £286000. The main raw material being used in a HRSG is water, which is converted to steam. Water at 60p/tonne for 8000 working hours a year costs , £120000.

The plant is designed to be highly efficient as well as being safe. Hazard studies were carried out at different stages to ensure the safety of the staff as well as the equipment.

  1. Introduction

Civ-Chem Engineering Solutions was approached to design a effluent treatment plant and a  CHP. The CHP to designed is to provide steam at temperature 183 °C and pressure 7 bar whereas the effluent treatment plant has to reduce the BOD and COD that is discharged to the sewer system.

 In a CHP the air is first compressed, after this the natural gas enter the combustion chamber along with air. They react o produce water and CO2. The gas enters the turbine and where it used to the turbine, hence the thermal energy is converted to kinetic energy.  The exhaust gas from the turbine is sent to the HRSG, where it is used to turn water into steam, hence recovering some of the heat. The exhaust gas allows only 12.5 tonne/hr of steam to be produced where as the requirement is 25 tonne/hr, so through supplementary firing the temperature of the exhaust gas is increased to meet the requirements of steam generation.

In a effluent treatment plant, the COD, BOD and suspended solids in water. The first step is the equalisation. After this a primary system is used to remove the suspended solids from the COD. In the secondary treatment the COD and TSS are further removed. The next step is the sludge de-watering, where water is removed from sludge.  

  1. Main Design ( Heat Recovery Steam Generator)

  1. Background

Heat recovery boilers are  an essential part of cogeneration systems today. In a cogeneration system the gas turbine produces hot exhaust gases and the heat recovery system recovers heat from the exhaust gas to generate steam for further use. There are different types of heat recovery systems and they are as follows

  • Heat Recovery Steam Generators (HRSGs)
  • Waste Heat Recovery Boilers (WHRBs)

WHRBs are  mostly used in process industry where as HRSGs are used in power plants. This makes HRSG an ideal choice for producing steam in a cogeneration system. HRSGs are integral part of cogeneration plants working at the backend of gas turbines. A HRSG is different from a conventional boiler in several ways, some of them are listed below,

  • A HRSG is smaller and less complex than a coal fired boiler
  • HRSGs are lighter on control instrumentation
  • HRSG are different in concept and construction as they have no fans, no refractory, no ash concerns and completely finned tubes.

HRSGs can be divided into subcategories according to what is required of them. HRSGs can be horizontal or vertical, fired or unfired and have natural or forced convection. HRSGs come in different shapes and with different features, the design is chosen on the basis of steam requirement and cost. The feature to choose in a HRSG are listed below,

  • Horizontal or Vertical Heat Recovery Steam Generators
  • Fired or Unfired Heat Recovery Steam Generators
  • Forced or Natural Circulation

  1. Design information

As it was mentioned in the section before that HRSGs can be built with different features, these features are chosen according to what is required from the heat recovery boiler. The first selection that has to be made is between a horizontal and vertical HRSG. After analysing the space available for the CHP plant, vertical HRSG was preferred because it is more compact. Usually the HRSG has a economizer, evaporator and super-heater, but in out design we don't need a super-heater as the steam being produced is already at a temperature higher than at which it is used in the plant. The pinch point worked out from the energy balance is 12 °C, to make it smaller a super-heater can be added but that would make the design a lot more expensive .The vertical HRSG which is going to be used for heat recovery will have the following feature:

  1. The evaporator and economizer coils are arranged horizontally with the flue gas travelling vertically upwards.
  2. There will be one economizer, one evaporator and one steam drum as multiple units are used for high temperature and high pressure steam. Conventionally HRSG units have a super-heater as well, to increase the temperature of the steam above its saturation point, however one is not required in this design because steam being produced is already at a higher temperature and pressure than  required for use in the plant.
  3. The structure is heavy as it supports the weight of the stack as well the tubes. The structure is taller but more compact than a horizontal HRSG. The structure also supports the steam drum.
  4. There is smaller footprint cause of the vertical design.

The second feature that has to selected is the type of circulation. HRSGs are capable of having both forced and natural circulation, but in a vertical HRSG it is preferred to have forced circulation, so in our design water will be introduced into the HRSG by using pumps. There will also be another pump, which will be used to pump water into the economizer from storage. The most significant disadvantage of having forced circulation is that if the pump fails, the HRSG will have to be shut down, but there is usually a backup pump so that doesn't happen. Forced circulations allows the structure to remain small as evaporator and economizer tubes can have  a smaller diameter.

The third design choice that has to be made for a HRSG is between being fired or unfired. The flue gas coming from the gas turbine is at 500 °C at a flow-rate of 75000 kg/hr which can produce steam at rate of 12.5 tonne/hr. So supplementary firing is needed to increase the temperature of flue gas to ensure that the steam production is 25000 kg.hr. In a vertical HRSG, the most common mean of supplementary firing is through a duct burner, the design for which will be discussed in the secondary design section.

To summarize the chosen design, the HRSG being using in the design is a vertical HRSG, with forced circulation and supplementary firing. After this the components of a HRSG have to be designed but before that energy and mass balance have to be carried out. The first step is to decide a figure point and the pinch point. The approach point is the difference between the economizer outlet water temperature and the saturation temperature of the steam. By working out the . After doing the energy  balance the approach point was worked out to be    8 °C. The pinch point for an HRSG is the difference between the saturation temperature and the temperature of flue gas leaving the HRSG, from the energy balance this was out to be    12 °C. The pinch is low enough to be economical as well ensuring that the HRSG is not too big. The graph below shows the change in temperature of the flue gas and water/steam as well as the approach and pinch point.

Join now!

  1. Material balance

The flue gas comes from the gas turbine at a flow rate of 75000 kg/hr  and temperature of   500 °C. The temperature of the flue gas only allows to generate 12500 kg/hr of steam where as the design requirement is 25000 kg/hr. So through supplementary firing the temperature of the flue gas will be increased to around 900 so that the steam requirement can be met. The flue gas entering the HRSG will have a different composition than the flue gas leaving the gas turbine, because some of the oxygen content in the flue will ...

This is a preview of the whole essay