The Plan.

It was as early as 1815 that Francis Greenway proposed or introduced the thought of building a bridge from the northern to the southern shore of the harbour.

It took some time for this to become a reality with design entries invited in 1900. All the submissions were considered unsuitable and so the momentum for the bridge crossing stopped.

However, after the First World War more serious plans were made, with a general design for the Sydney Harbour Bridge prepared by Dr J J C Bradfield and officers of the NSW Department of Public Works. The New South Wales Government then invited worldwide tenders for the construction of the Bridge in 1922 and the contract was let to an English firm Dorman Long and Co of Middlesbrough.

Introduction of the Bridge

The Sydney Harbour Bridge is the world's largest, but not longest steel arch bridge. The Harbour Bridge is one of the most famous landmarks in Sydney. Completed in 1932, the construction on the bridge began in December, 1926 and was an incredible achievement and a huge engineering accomplishment. Prior to the bridge being built, the only links, roads or transport between the city centre in the south and the residential north were by ferry or by a 20 kilometre road trip that involved the crossing of five bridges.

Sydney Harbour Bridge & its Construction

The contractors set up two workshops at Milsons Point on the North Shore. Here 79% of the steel was imported from England and 21% used from Australian sources was used into the making of this full steel arch bridge. The foundations for the four main bearings, which carry the full weight of the main span were dug to a depth of 12.2 metres and filled with special reinforced high-grade concrete laid in hexagonal formations.

                

Four giant 89 metre high pylons are made out of concrete, faced with granite, quarried near Moruya, where about 250 Australian, Scottish and Italian stonemasons and their families lived in a “temporary settlement”. Three ships were made specifically to carry the contents of 18,000 cubic metres of cut, dressed and numbered granite blocks, 300km north to Sydney.

Join now!

After the spans were constructed the work began on the hardest and most vital part of the bridge, the main arch. Two half-arches were built out progressively from each shore, each held back by 128 thick cables anchored underground through U-shaped tunnels. Steel members were fabricated in the workshops, placed onto barges, towed into position on the water out from the harbour and lifted up by two 580 tonne loads of electrically operated ‘creeper cranes’, which erected the half-arches before them as they travelled forward.

Joining of the Arches

On the 19th of August 1930 the arch of the ...

This is a preview of the whole essay